Our first equipment arrived late October, 2006. The rains had already
started, work on the right-of-way was difficult due to the mud, so it
was temporarily suspended.
Since it was important to find a dry place for the new equipment it was
decided to switch effort to building an engine house.. The only space
available was an area directly behind the play yard. Due to the slope of
the land it required up to 3 feet of soil to be excavated and a
retaining wall built. (in hindsight, any other location would
have been better). The very atypical constant drizzle we experienced
through much of November and December made the excavation difficult as
the tractor could not get a grip in the slimy clay.
When the cut was nearing completion at the end of December, the tractor
clipped the top of a previously unknown 4" pipe that went to a leach
field. In no time at all, the cut was full of a very foul smelling
liquid. After many bucket trips and thankfully a few sunny days in early
January, we were able to repair the pipe, finish the cut, put in
the drain field and back-fill with gravel.
Work was immediately started on the RR tie foundation, and then the
walls.
An early opportunity came up to lay some track, so the wall work was
temporarily stopped until the first track was placed.
The photos below outline the project to date:
|

First Cut with the tractor
|

Cut finished
|
|

Fence post hanging
|

Drain pipe being installed
|
|

First layer of gravel
|

Tie foundation being installed
|
|

Tie foundation is in place and second layer retaining wall started
|

First curved wall in place
|
|

How the mud sill was pre-bent
|

Ready for rail
|
|
|
|
|
|
|
| |
|
| |
|
| |
|
| |
|
|